  • Expert supervision and control tests of the rehabilitation works on the expansion joint on the viaduct Veliki Svib at the highway A6 Zagreb – Rijeka
  • Supervision services contract for the execution of works on the reconstruction of the left embankments of Pušćine
  • Expert supervision and control tests of the rehabilitation works of the road asphalt surfacing at the highway A3 Bregana – Zagreb – Lipovac from km 74+800 to km 80+550 (left and right)
  • Expert supervision and control tests of the rehabilitation works of the road asphalt surfacing at the highway A3 Bregana – Zagreb – Lipovac from km 110+000 to km 114+000 (right)
  • Expert supervision and control tests of the rehabilitation works on the expansion joint on the viaduct Čičave at the highway A6 Zagreb – Rijeka
  • Expert supervision over water supply and drainage in the street Kodrmanova ulica – Phase 1
  • Supervision services contract for the execution of constructions works in the construction of the business building of the Feroterm logistics and distribution centre in Opuzen
  • Expert supervision and control tests of the rehabilitation works on the bridge Vočarica – left on km 134+820 at the highway A3 Bregana – Zagreb – Lipovac
  • Supervision services contract for the execution of construction work for building the composting plant Metković
  • Expert supervision and coordinator II for safety and health at work on the reconstruction and extension of internal and external drainage at the highway A1 Zagreb – Split – Dubrovnik, section Maslenica – Zadar 1
  • Professional supervision of the rehabilitation works on the Velika Mlaka overpass
  • Professional supervision and control tests of the rehabilitation works on the Nova Zelina bridge at km 56+946, A3 motorway Bregana – Zagreb – Lipovac
  • Professional supervision of the rehabilitation of pedestrian lanes on the  Duman viaduct at km 158+430, A1 motorway Zagreb – Split – Dubrovnik
  • Professional supervision and control tests of the rehabilitation works on the Smolčić overpass at km 211+114, A1 motorway Zagreb – Split – Dubrovnik
  • Professional supervision of the rehabilitation works on the sewerage system of the official passage at km 148+430, A1 motorway Zagreb – Split – Dubrovnik
  • Professional supervision and control tests of the rehabilitation works on the expansion joints of the Dobra bridge at km 52+243, A1 motorway Zagreb – Split – Dubrovnik
  • Professional supervision of the construction works on the water supply network in Dubranec
  • Professional supervision services of the replacement culvert construction in Mala Kosnica
  • Supervision of the sewerage collector construction from the wastewater treatment device of the Nova Gradiška agglomeration to the recipient at the Visoka Greda site
  • Professional supervision of the construction of the sewerage network of the Gornji and Donji Jarek settlements
  • Professional supervision and Occupational Health and Safety Coordinator II services in the “Reconstruction of the Dubravica waste landfill, Phase 4 in Metković“ project
  • Professional supervision and control tests of the rehabilitation works on the Perušić overpass at km 170+096 and the Gospić traffic junction at km 181+362, A1 motorway Zagreb – Split – Dubrovnik
  • Professional supervision and control tests of the rehabilitation of the bridge over the diversion canal at km 21+325, A4 motorway Zagreb – Goričan
  • Professional supervision of the reconstruction of public canals in Jabukovac, Paunovac and Slavujevac streets in Tuškanac
  • Professional supervision of the works on cleaning the Trakošćan accumulation lake from deposited sediments
  • Supervision services in the implementation of the “Collection, drainage and wastewater treatment system of the Vrbovec agglomeration“ EU project
  • Professional supervision of the construction of the Donje polje – Jadrtovac public irrigation system
  • Professional supervision of the construction of the water reservoir in Vid
  • Supervision service for the project of improving the water community infrastructure of the Zaprešić agglomeration
  • Contract on services for supervision of works on the construction of the collection, drainage and wastewater treatment system of the agglomeration Metković
  • Supervision services for the construction of the drainage system of the agglomeration Opuzen – part of canal Mala Neretva
  • Works performance supervision services – construction of the Bodovaljci – Laze – Godinjak water supply pipeline
  • Expert supervision services on works – water supply of the Municipality of Staro Petrovo Selo – construction of connections in Staro Petrovo Selo, Godinjak, Vrbova, Štivica, Komarnica
  • Expert supervision of the construction (extension) of the water supply network in the area of the city district Podsused-Vrapče
  • Expert construction supervision during the execution of works – Regulation of the river Orljava in the area of Ciglenik and Bečic
  • Professional supervision of the rehabilitation of the transition devices of the Drava I bridge, highway A4 at km 23+220
  • Expert supervision of the construction of the wastewater drainage system – sanitary sewerage stage 2
  • Expert supervision of the construction of the water supply pipeline in the villages of Taborište, Hrastovica and Donja Budičina
  • Expert supervision and safety at work coordinator services during the works execution stage of the project “Construction of the Duga ulica Street–Borinačka ulica Street overpass and an access road in the city of Vinkovci”
  • Expert supervision of: Loss control management system – upgrading the existing supervision-management system by establishing control and reducing losses in the water supply system of the public supplier of water supply services
  • Professional supervision over the implementation of the project “Waste water collection and treatment system of Velika Gorica agglomeration” (Sustav odvodnje i pročišćavanja otpadnih voda aglomeracije Velika Gorica)
  • Complete professional supervision over the implementation of the project “Improvement of water utility infrastructure in the area of Vinkovci, Otok, Cerna and Ivankovo agglomeration” (Poboljšanja vodnokomunalne infrastrukture na području aglomeracija Vinkovci, Otok, Cerna i Ivankovo)
  • Professional supervision of implementing the project of water supply reconstruction, reconstruction and construction of drainage system and the construction of wastewater treatment device in Petrinja agglomeration
  • Expert supervision and OSH Coordinator II services in the implementation of the project “Waste Water Collection, Drainage and Treatment System in the Nova Gradiška Agglomeration
  • Development of the project documentation for the main design of the construction of the connecting water supply pipeline in the Vukovinsko polje – Vukovina work zone
  • Project documentation preparation for the construction of the connecting pipeline VS “Baltić Brdo” in Glina
  • Project documentation preparation for the construction of the pumping station “Baltić Brdo” in Glina
  • Preliminary, main and detailed design for the reconstruction of the state road DC22, section Cubinec – Sveti Ivan Žabno with obtaining a location and construction permit
  • Preparation of project and technical documentation for the reconstruction of the street Lučko in Zagreb
  • Development of the main – detailed design of the reconstruction of Nova cesta – Zadarska ulica
  • Preparation of the study and project documentation on procurement for project application Bjelovar 2, “Improvement of the municipal water infrastructure in the area of agglomerations Bjelovar, Gudovac and Rovišće”
  • Preparation of the conceptual design and master project for the construction of the water supply pipeline in Trg dr. F. Tuđmana Street, Ulica žrtava domovinskog rata Street and Hrvatska ulica Street in Glina
  • Preparation of project documentation for bus stop construction city of Sisak
  • Preparing the project documentation for the construction of water supply pipelines and public canals in the city district of Podsljeme; Water supply pipeline in streets: Prostišno, Podrebernica, Šestinski prilaz, Draškovec, Rijeznica and Topolje
  • Preparing the conceptual, main and detailed designs of the public canal project in the extension of Kameščica Street (Čučerska Road, from house No. 374)
  • Drawing up project documents for the reconstruction of the pavement of the state road DC41 at the part Koprivnička Rijeka – Vojakovački Kloštar
  • Drawing up of project documents and fire protection studies for construction of the water supply pipelines in the city area Brezovica
  • Drawing up of the preliminary project layout, main and execution plan with obtaining a location and construction permit for the reconstruction of the state road DC22, road part Guščerovec-Križevci, 6.5 km long
  • Preparation the detailed project documentation of Miholjac – Viljevo subsystem within the Karašica irrigation system
  • Project documentation preparation service for the Miholjački Poreč subsystem within the Krašica irrigation system
  • Project management services for the construction of the wastewater collection channel of the places Dobrodol, Šimunčevec and Vuger Selo in Sesvete – the basin of the “Šimunčevećka” collection channel
  • Project management services for the complete renovation of buildings damaged in the earthquake for the needs of the Faculty of Agriculture of the University of Zagreb
  • Project management of the “Construction and equipping of the biological treatment plant for separately collected biowaste“ of the Town of Bjelovar
  • Project management of the construction and reconstruction of the water-utility infastructure of the Slatina agglomeration
  • Project management of the construction and equipping of the sorting plant for separately collected waste of the Town of Bjelovar
  • Project management of the construction of the Glina – Maja – Dragotina main pipeline
  • Provision of consulting services for the construction project management for the contract for works on the reconstruction and extension of the building of the riding yard (“zgrada jašionice”) for the Land Registry Department of the Civil Court in Zagreb
  • Project management for the construction of the pre-pump station Jalševec, the water supply pipeline in settlements Oporovečki Breg, Jalševec and Sveta Barbara as well as water tank Sveta Barbara
  • Project management for the construction and reconstruction of public ducts in Južna ulica Street and street branches
  • Coordinator II services in the Dubranec II water supply network construction project
  • Preparation of a geodetic study of communal infrastructure in Čabar
  • Surveying services Donje Taborište
  • Surveying services Majske Poljane
  • Preparation of allotment surveys of the formation of plots for the construction project of hydrotechnical facilities for flood defence on the left and right banks of Glina, at the settlements Topusko and Velika Vranovina
  • Preparation of project documents for the construction of water supply for the settlements Pokupska Slatina, Zaloj, Gračenica Šišinečka and Stankovac
  • Development of the plotting study for cadastral plot No 1670, cadastral municipality Glina, obtaining the decision on the establishment of the building plot and implementing the subject decision for the purpose of registering data on buildings on cadastral plot No 2324/1, cadastral municipality Knin
  • Geodetic supervision of the construction works in Branimirova street in Sesvete from Zagrebačka road to Brestovačka street, Stage I
  • Development of cadastre and land registry alignment documents, plotting study and building plot formation for the project “Reconstruction of the Sava embankment on its right bank from Slunjski promenade to Gradusa, Stage IV”
  • Development of the surveying study for staking-out of the building and staking-out of the building, development of the surveying study for registering the construction work in the cadastre and land registry Mraclin
  • Geodetic and cadastral services for registration of unclassified roads Krašić
  • Development of geodetic bases for the equipping of bus stops for the Town of Sisak
  • Development of surveying and plotting studies for the Central State Office for Reconstruction and Housing Care
  • Development of geodetic bases for the construction of water supply pipelines and public canals in the Podsljeme city district
  • Professional geodetic supervision of the construction works at the separation point of the Ogulin retention, phase I.
  • Geodetic basis for the construction of the connecting pipeline VS “Baltić Brdo”.
  • Geodetic basis for the preparation of project documentation for the construction of the pumping station “Baltić Brdo”.
  • Geodetic bases for the development of the preliminary and main design for the construction of a water supply pipeline in the street Ulica Trg Dr. Franje Tuđmana, Ulica žrtava Domovinskog rata and Hrvatska ulica in Glina
  • Professional geodetic supervision of the execution of works with the preparation of a geodetic survey of the as-built situation and the preparation of studies for registration in the cadastre and land register certified by the regional office for the project of regulation of the river Orljava
  • Geodetic works as part of the preparation of project documentation for the reconstruction of the pavement of the state road marked DC41, section Koprivnička Rijeka-Vojakovački Kloštar, length 6.8 km.
  • Geodetic works as part of the development of the preliminary, main and detailed design for the reconstruction of the state road marked DC22, section Cubinec-Sveti Ivan Žabno, length 8.4 km
  • Geodetic basis for the preparation of project documentation for the construction of bus stops city of Sisak
  • Geodetic basis for the preparation of the main and detailed design for the reconstruction of the street Nova cesta – Zadarska ulica
  • Preparation of a land parcellation survey study for the project “Črnac Duct Regulation”